Power assets and projects · AUS · aemo_generation

Tarraleah Redevelopment

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Unit Capacity (MW AC)100 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-e30c1a40c6bb5332e6f9288b
Aggregated Nameplate Capacity (MW AC)100 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-e30c1a40c6bb5332e6f9288b
Detailed source fields
Original source fieldPublished value or condition
Survey ID2014
Site NameTarraleah Redevelopment
KCI IdT00018
Site OwnerHYDROTAS
RegionTAS1
Max Site Capacity (AC)190
Gen Info Unit ID201402
Unit Name2
Technology TypeHydro
Technology DetailDam
Dispatch TypeScheduled
Unit Count1
Unit Capacity (MW AC)100
Aggregated Nameplate Capacity (MW AC)100
Commitment StatusPublicly Announced
Survey Last Requested Date2026-03-10T00:00:00
Survey Latest Update Date2026-03-24T17:50:25
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:1472

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:1472

Sources EV-e30c1a40c6bb5332e6f9288b
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 b5703e7459b7fbf85610f69279d6ae84e883abb8c11e7c856719dbdeab679ec6

Usage terms AEMO general copyright permission subject to exceptions

Source snapshots by date · AUS · aemo_generation

Tarraleah Redevelopment

Generation-register unit · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Survey ID2014
Site NameTarraleah Redevelopment
KCI IdT00018
Site OwnerHYDROTAS
RegionTAS1
Max Site Capacity (AC)190
Gen Info Unit ID201402
Unit Name2
Technology TypeHydro
Technology DetailDam
Dispatch TypeScheduled
Unit Count1
Unit Capacity (MW AC)100
Aggregated Nameplate Capacity (MW AC)100
Commitment StatusPublicly Announced
Survey Last Requested Date2026-03-10T00:00:00
Survey Latest Update Date2026-03-24T17:50:25
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:1472

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:1472

Sources EV-e30c1a40c6bb5332e6f9288b
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 b5703e7459b7fbf85610f69279d6ae84e883abb8c11e7c856719dbdeab679ec6

Usage terms AEMO general copyright permission subject to exceptions

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel