Power assets and projects · AUS · aemo_generation

Baroota Pumped Hydro Project

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Unit Capacity (MW AC)125 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-3d8bfdf92488ba4bea703dfa
Aggregated Nameplate Capacity (MW AC)250 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-3d8bfdf92488ba4bea703dfa
Detailed source fields
Original source fieldPublished value or condition
Survey ID1682
Site NameBaroota Pumped Hydro Project
Site OwnerACEN Renewables
RegionSA1
Max Site Capacity (AC)250
Gen Info Unit ID168202
Unit Nameunit 1-2
Technology TypeHydro
Technology DetailDam
Dispatch TypeScheduled
Unit Count2
Unit Capacity (MW AC)125
Aggregated Nameplate Capacity (MW AC)250
Commitment StatusPublicly Announced
Full Commercial Use Date2034-12-01T00:00:00
Expected Closure Year2072
Survey Last Requested Date2026-12-05T00:00:00
Survey Latest Update Date2026-05-13T13:49:37
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:67

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:67

Sources EV-3d8bfdf92488ba4bea703dfa
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 5e7b649434a065b109dd28255bc2f3f67b1ca11be9499e577b0240664b518841

Usage terms AEMO general copyright permission subject to exceptions

Source snapshots by date · AUS · aemo_generation

Baroota Pumped Hydro Project

Generation-register unit · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Survey ID1682
Site NameBaroota Pumped Hydro Project
Site OwnerACEN Renewables
RegionSA1
Max Site Capacity (AC)250
Gen Info Unit ID168202
Unit Nameunit 1-2
Technology TypeHydro
Technology DetailDam
Dispatch TypeScheduled
Unit Count2
Unit Capacity (MW AC)125
Aggregated Nameplate Capacity (MW AC)250
Commitment StatusPublicly Announced
Full Commercial Use Date2034-12-01T00:00:00
Expected Closure Year2072
Survey Last Requested Date2026-12-05T00:00:00
Survey Latest Update Date2026-05-13T13:49:37
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:67

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:67

Sources EV-3d8bfdf92488ba4bea703dfa
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 5e7b649434a065b109dd28255bc2f3f67b1ca11be9499e577b0240664b518841

Usage terms AEMO general copyright permission subject to exceptions

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel