Electricity
Calculate the total facility load based on the target IT load and PUE, and verify the supply voltage, grid connection, supply schedule, and reinforcement scope in writing.
Power Connection Procedures →KOREA DATA CENTER EVIDENCE GUIDE
This page does not serve as a substitute for land acquisition or feasibility conclusions; rather, it provides the sequence for verifying the permits, power, and telecommunications requirements necessary for data center development. Applications for electricity service and grid reviews are Practical Guide to Power Connection, KEPCO, the Korea Electric Power Evaluation Institute, and the Energy Council Overall Process and Required Vendors, Contracts, and Documents, Actual licensing records are National Licensing Database, The basis for telecommunications is Database of Telecommunications Access PointsWe cross-check this information.
SITE EVIDENCE
Calculate the total facility load based on the target IT load and PUE, and verify the supply voltage, grid connection, supply schedule, and reinforcement scope in writing.
Power Connection Procedures →It takes into account not only the site area, building coverage ratio, and floor area ratio, but also substation, power generation, and cooling facilities; separation distances; equipment delivery; and space for phased expansion.
Free Data Center Site Analysis →Distinguish between land use zones and districts, the permissibility of broadcasting and telecommunications facilities, and consultations regarding development activities, construction, transportation, disasters, the environment, and fire safety, as well as the possibility of inheriting existing permits.
Permit and Licensing Procedures →Distinguish between the availability of telecom services and data center-level dual entry, and verify the physical paths for different central offices, PoPs, ducts, and directions.
Database of Telecommunications Access Points →Distinguish between the source of land rights, the possibility of inheriting existing permits, approvals, and agreements regarding power and telecommunications, and the boundaries of planned and finalized information in the source text and the data room.
Public Information on Sites and Development →Check the land use zones and districts, land classifications, development activities, roads, water and sewer systems, telecommunications, building coverage ratio, floor area ratio, and the permitting conditions for broadcasting and telecommunications facilities.
Submission of Site Review Applications →A project is not considered complete based on a building permit alone. Distinguish between development activities, consultations regarding transportation, environment, disaster management, fire safety, and information and communications, and the dates for permits, groundbreaking, and occupancy permits.
Data Center Licensing Procedures →Separate the target power reception capacity from the IT load and PUE, and verify the nearby substation, power supply route, power reception voltage, KEPCO supply agreement, and whether a grid impact assessment has been conducted.
Practical Guide to Power Connection →Data halls, transformers, UPS systems, generators, power distribution, cooling, fire protection, and security systems, as well as phased expansions, are all incorporated into the architectural, electrical, mechanical, and telecommunications designs.
Database of Design and Construction Management (CM) Firms →We distinguish between land costs, power connection fees, construction costs, financing costs, and contingency reserves, and review equity, project financing (PF), and sale structures in accordance with power supply, permitting, and tenant conditions.
Database of Financial and Project Finance (PF) Companies →Distinguish between EPC (Engineering, Procurement, and Construction) and specialized construction, and reflect in the contract the responsibilities for FAT, SAT, and IST; thermal load testing; Tier preparation; and defect resolution.
Database of Construction and Verification Companies →Completion and occupancy permits differ from actual commercial operation. Verify available IT MW, rack density, cooling methods, network and cloud connectivity, SLAs, and the move-in date.
Database of Operators and Leasing Companies →EVIDENCE FIRST
National Center for Legal Information · Verified on August 30, 2026
View source →Korea Electric Power Corporation ON · Verified on August 30, 2026
View source →AI-DC KOREA Practical Guide · Verified on August 30, 2026
View source →AI-DC KOREA Actual Database · Verified on August 30, 2026
View source →AI-DC KOREA Telecommunications Database · Verified on August 30, 2026
View source →SEARCH TOPICS
Data Center Permits, Data Center Licensing Procedures, Licensing Agency Services, Building Permits, Development Permits, Notice of Construction Commencement, Occupancy Permits
Data center electricity, data center power, KEPCO electricity service application, power supply capacity, distance to substation, power connection, grid impact assessment
Data center architectural design, electrical design, MEP, UPS, generators, power distribution, liquid cooling, commissioning
Data Center Project Financing (PF), Investment Attraction, Asset Management, Divestiture, Colocation Leasing, IT MW Demand
FREQUENT QUESTIONS
Check land use, zoning, development activities, roads and infrastructure, building coverage ratio and floor area ratio, as well as the conditions for broadcasting and telecommunications facilities and the feasibility of power connection, all by lot number.
No. Building permits, KEPCO supply agreements, electricity usage contracts, and power supply capacity must be verified based on separate documentation.
The development project manager can comprehensively manage site reviews, the list of permits and licenses, the division of labor among agencies and specialized firms, as well as schedules, supplementary requirements, and permit conditions. Tasks requiring specialized qualifications—such as design, evaluation, and legal matters—are performed by the relevant specialized agencies.
After calculating the facility load based on the target IT load and PUE, we verify the desired supply voltage, usage period, grid connection, service entrance route, reinforcement work, and the need for a grid impact assessment by categorizing them into consultation documents with Korea Electric Power Corporation (KEPCO).
No. The required application capacity is reviewed separately by applying facility loads—such as cooling and electrical equipment—as well as PUE, reserve margins, and power factor to the IT load.
Land costs, power connection fees, construction and MEP costs, design, evaluation, and permitting fees, contingency reserves, and financing costs are itemized and cross-checked based on IT MW and gross floor area.
Calculations must be performed for each project site by factoring in the target IT load, rack density, architectural and equipment configurations, statutory building coverage and floor area ratios, separation distances, and the scope for future expansion.
No. The distance to the substation is an estimated value; the actual grid connection, available capacity, reinforcement work, feed-in route, and supply schedule must be confirmed through consultation documents from KEPCO.
No. You must verify not only whether the telecommunications carriers are different but also whether the central office, PoP, duct, access direction, and physical path are actually separate.
First, we identify potential land, power, and telecommunications sites through a free address analysis. Once we receive your submitted materials, we review the scope of any necessary supplements to the permitting, design, and investment documentation.
Online materials do not guarantee building permits, power supply from KEPCO, financial financing, or investment approval. Final decisions must be made based on official documents for each project site and verification by relevant agencies and specialized firms.