Auchentiber Farm 700MW BESS
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8c68af2255616be4bec37ca1 |
| MW Increase / Decrease | 700 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8c68af2255616be4bec37ca1 |
| Cumulative Total Capacity (MW) | 700 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8c68af2255616be4bec37ca1 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Auchentiber Farm 700MW BESS |
| Customer Name | GPC 700 Ltd |
| Connection Site | Auchentiber Farm BESS 400kV Substation |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 700.00 |
| Cumulative Total Capacity (MW) | 700.00 |
| MW Effective From | 2029-10-17 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | SPT |
| Plant Type | Energy Storage System |
| Project ID | a0l8e0000011zs9AAA |
| Project Number | PRO-003601 |
| Gate | Not obtained |
| Original text | Scoping |
| source_record_id | csv:row:91 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:91
Sources EV-8c68af2255616be4bec37ca1Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 77eb4a78ec49764ebff4a7d0da9b30eeb0984050683a40cf5175496d6699ab69
Usage terms NESO Open Data Licence