Carey Farm PV
Connection register · consented
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Consents Approved As-of date 2026-10-01 Sources EV-3543c67b9280df6a10bb1efc |
| MW Increase / Decrease | 9.9 MW | Original source column definition · project stage · Consents Approved As-of date 2026-10-01 Sources EV-3543c67b9280df6a10bb1efc |
| Cumulative Total Capacity (MW) | 9.9 MW | Original source column definition · project stage · Consents Approved As-of date 2026-10-01 Sources EV-3543c67b9280df6a10bb1efc |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Carey Farm PV |
| Customer Name | Scottish Hydro Electric Power Distribution Plc |
| Connection Site | Abernethy GSP |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 9.90 |
| Cumulative Total Capacity (MW) | 9.90 |
| MW Effective From | 2024-05-31 |
| Project Status | Consents Approved |
| HOST TO | SHET |
| Plant Type | PV Array (Photo Voltaic/solar) |
| Project ID | a0l4L0000005iiTQAQ |
| Project Number | PRO-001170 |
| Gate | Not obtained |
| Original text | Consents Approved |
| source_record_id | csv:row:120 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:120
Sources EV-3543c67b9280df6a10bb1efcEvidence SHA-256 2feb369e26e2a57bf5656824c32190410d8889b1e9d9a06a1bbb6c2c3e49f21b
행 SHA-256 5d74eed2a1abee75be52d600fdc770ae5094cbdff216a3088d7500f506190b7f
Usage terms NESO Open Data Licence