If a substation is nearby, Is securing power enough?
Finding a nearby substation on a map is just the starting point. To determine a data center’s power schedule, you must also verify the grid’s available capacity, the connection timeline, live and standby circuits, the actual 154 kV feed-in route, and who is responsible for construction.
1 / 10 · AI-DC KOREA Webtoon Episode 2: Does Having a Substation Nearby Mean Power Supply Is Secured?2 / 10 · Even if a substation is located nearby, that does not mean electricity can be used immediately.3 / 10 · If there is no spare capacity in the power grid, connection to even a nearby substation is not possible.4 / 10 · The date when access becomes available must align with the data center’s completion schedule.5 / 10 · Distinguish between the capacity, circuits, switching methods, and ownership boundaries of commercial power and reserve power.6 / 10 · The 154 kV feeder connection is evaluated based on the actual feasible construction route, not the straight-line distance.7 / 10 · Consultation with KEPCO is required at each stage, from the submission of an electricity service application to the finalization of the supply plan.8 / 10 · Compare land costs, power connection fees, grid reinforcement costs, and the completion schedule to the total development cost.9 / 10 · AI-DC KOREA begins a preliminary site analysis based on the address.10 / 10 · Actual supply capacity and connection schedules are more important than the proximity of a substation.Key Points
Check availability and connection schedules rather than distance.
Even if a substation is nearby, the data center development schedule may not be feasible if there is no remaining capacity in the power system or if the wait time for connection and reinforcement work is prolonged. Commercial power and reserve power must be verified separately in terms of capacity, circuit configuration, switching methods, metering, and ownership boundaries; the total capacity should not be interpreted as IT load that can be used simultaneously.
The 154 kV service line must be evaluated based on the actual route—which takes into account roads, ditches, right-of-way occupancy, public complaints, and construction conditions—rather than the straight-line distance on a map. Since the receipt of an electricity service application does not guarantee supply, documentation must be managed on a step-by-step basis until the connection point, scope of work, fees, and estimated supply start date are confirmed.