Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · AUS · aemo_generation
Belah BESS
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Unit Capacity (MW AC)
0.45 MWac
Original source column definition · Generation-register unit · Publicly Announced As-of date 2026-07-31 Sources EV-ad1717be2dc86865526bc3ca
Aggregated Nameplate Capacity (MW AC)
460.8 MWac
Original source column definition · Generation-register unit · Publicly Announced As-of date 2026-07-31 Sources EV-ad1717be2dc86865526bc3ca
Agg Nameplate Storage Capacity (MWh)
1771.52 MWh
Original source column definition · Generation-register unit · Publicly Announced As-of date 2026-07-31 Sources EV-ad1717be2dc86865526bc3ca
Detailed source fields
Original source field
Published value or condition
Survey ID
3152
Site Name
Belah BESS
KCI Id
Q00265
Site Owner
Eku Energy Projects (Australia) Pty Ltd as trustee for the Eku Energy Projects Australia Trust