Public consultation on AIDC implementing regulations: the proposed 50 MW exception outside the Seoul Capital Area and treatment of existing applications

The draft AIDC Enforcement Decree and Enforcement Rules released on November 20 propose a contracted-power threshold of 50 MW or less for exclusion from electricity grid impact assessment outside the Seoul Capital Area. Expansion and conversion projects would be assessed using total contracted power after completion. Comments may be submitted through December 30.

ORIGINAL SOURCE

Original sources and attachments

Read the original material, then review the key facts and AIDC analysis below.
Original text of the AIDC Special Act's draft Enforcement Decree

Notification under Article 7; the 50 MW and total contracted power criteria in Article 17; transitional supplementary provisions

Read the complete source ↗
Excerpts from the legislation or notice

2026년 11월 20일 입법예고안 · 시행 전 제정안

제17조(전력계통영향평가 면제 전력용량)

① 법 제19조제2항에 따라 전력계통영향평가를 면제받을 수 있는 전력용량은 전기판매사업자와 전기사용계약을 체결하려는 최대수요전력(이하 “계약전력”이라 한다)을 기준으로 50메가와트 이하로 한다. ② 인공지능 데이터센터를 확장하거나 데이터센터를 인공지능 데이터센터로 전환하는 경우에는 확장 또는 전환 후의 총 계약전력을 기준으로 산정한다.

Read the complete text and other provisions ↗
Source publication date2026-11-20Source review date 2026-11-20Site update date 2026-11-20
Project SiteNationwide framework · special grid impact assessment provisions outside the Seoul Capital Area
Parties involvedMinistry of Science and ICT · Ministry of Climate, Energy and Environment · AIDC businesses
Current StagePublic consultation · before promulgation of the final implementing regulations

VERIFIED FACTS

Key points identified in the original text

01Public consultation period: November 20–December 30, 2026
02AIDC special act effective date: March 10, 2027
03Article 17 of the draft Enforcement Decree: contracted power of 50 MW or less, calculated using total contracted power after expansion or conversion
04Distinguish the proposed consultation-draft criteria from current grid impact assessment obligations
05The waiver of nontechnical assessment in AIDC special zones and priority assessment are planned follow-up measures requiring notices and manuals

AI-DC KOREA ANALYSIS

Interpretation and the following points to verify

This public consultation does not immediately change the current grid impact assessment rules or require all existing KEPCO applications to be submitted again. The requirements must be checked against the special act taking effect on March 10, 2027 and the final implementing regulations. Projects with existing applications must distinguish the advance notice, electricity-use application and contract from the notice of grid assessment results, and separately review assessment reapplication and KEPCO amendment procedures when capacity, location or the planned date changes. Even when exclusion from assessment applies, power-supply review, grid reinforcement and other approvals, such as building permits, remain necessary.

RELATED POLICY

Related policy and dates

Check the implementation status and conditions of the same policy.
AnnouncementPublic consultation on the AIDC Special Act's draft Enforcement Decree and Enforcement Rules, including a proposed 50 MW exemptionDeadline for public comments on the draft legislation 2026-12-30 · View applicable conditions →

PRIMARY EVIDENCE

Source Materials

The external source text is provided for fact-checking purposes; the summary and stage-by-stage analysis have been organized on this page.
Public Participation Legislation Center · joint announcement by the relevant ministriesPublic consultation on AIDC implementing regulations: the proposed 50 MW exception outside the Seoul Capital Area and treatment of existing applications2026-11-20 · Open original text ↗

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel