LG Uplus announces phased opening plans for four Paju AIDC buildings
LG Uplus says it is building a 200MW utility-intake AI data center in Paju, with four buildings to open in stages by 2028. Building 1 has secured a customer and targets operation after completion in June 2027 at an announced scale of 50MW.
VERIFIED FACTS
Key points identified in the original text
AI-DC KOREA ANALYSIS
Interpretation and the following points to verify
The official newsroom posted this on November 6; the announcement was made on November 4. The 200MW figure is total utility-intake capacity; 50MW is Building 1's announced scale, not verified IT power or available capacity. This does not establish leases for all four buildings, completion or operating status. Quarterly AIDC revenue of KRW 131.7 billion covers the company segment, not Paju. No new main-contractor, design or equipment-supply contract relationships are confirmed.