Aberthaw BESS
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-d50018216bbc391377b613c5 |
| MW Increase / Decrease | 240 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-d50018216bbc391377b613c5 |
| Cumulative Total Capacity (MW) | 240 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-d50018216bbc391377b613c5 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Aberthaw BESS |
| Customer Name | REWE 7 LIMITED |
| Connection Site | Aberthaw B 275/132kV Substation |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 240.00 |
| Cumulative Total Capacity (MW) | 240.00 |
| MW Effective From | 2037-10-15 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | NGET |
| Plant Type | Energy Storage System |
| Project ID | a0l8e000000f65FAAQ |
| Project Number | PRO-003954 |
| Gate | 1 |
| Original text | Scoping |
| source_record_id | csv:row:11 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:11
Sources EV-d50018216bbc391377b613c5Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 16b571d142cfec492301af498be8cc6b35385936e7344eae818a0f34b4fde243
Usage terms NESO Open Data Licence