AGS Calderside Battery Energy Storage System
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-047fd9d259430767a3069b8d |
| MW Increase / Decrease | 200 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-047fd9d259430767a3069b8d |
| Cumulative Total Capacity (MW) | 500 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-047fd9d259430767a3069b8d |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | AGS Calderside Battery Energy Storage System |
| Customer Name | Advance Grid Solutions Limited |
| Connection Site | AGS CALDERSIDE 275KV SUBSTATION |
| Stage | 2.00 |
| MW Connected | 0.00 |
| MW Increase / Decrease | 200.00 |
| Cumulative Total Capacity (MW) | 500.00 |
| MW Effective From | 2033-10-31 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | SPT |
| Plant Type | Energy Storage System |
| Project ID | a0l8e0000010wexAAA |
| Project Number | PRO-002752-2 |
| Gate | Not obtained |
| Original text | Scoping |
| source_record_id | csv:row:26 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:26
Sources EV-047fd9d259430767a3069b8dEvidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 b48b9d9caf152502bc133c5ca6b81907d06e5506bd37da9cb03f0e447a21f56e
Usage terms NESO Open Data Licence