| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8403595e67bcb6b89ba3599d |
| MW Increase / Decrease | 150 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8403595e67bcb6b89ba3599d |
| Cumulative Total Capacity (MW) | 150 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-8403595e67bcb6b89ba3599d |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Afan Wind Farm and BESS |
| Customer Name | TRYDAN GWYRDD CYMRU (Welsh Government) Ltd |
| Connection Site | SOUTH WALES WEST CONNECTION NODE A 132KV SUBSTATION |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 150.00 |
| Cumulative Total Capacity (MW) | 150.00 |
| MW Effective From | 2036-12-06 |
| Project Status | Scoping |
| Agreement Type | Embedded |
| HOST TO | NGET |
| Plant Type | Energy Storage System;Wind Onshore |
| Project ID | a0l8e0000012i2aAAA |
| Project Number | PRO-004588 |
| Gate | Not obtained |
| Original text | Scoping |
| source_record_id | csv:row:22 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:22
Sources EV-8403595e67bcb6b89ba3599dEvidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 6f0e1db91bc8227ea4f454cdda5c4f7455d552d1c7fa994fd4aafd24f85e4972
Usage terms NESO Open Data Licence