180/181 Clynelish Muir BESS
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-20b891c892d345b9cbafa3d2 |
| MW Increase / Decrease | 50 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-20b891c892d345b9cbafa3d2 |
| Cumulative Total Capacity (MW) | 50 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-20b891c892d345b9cbafa3d2 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | 180/181 Clynelish Muir BESS |
| Customer Name | Opdenergy UK 19 Limited |
| Connection Site | BRORA 132/33KV GRID SUPPLY POINT SUBSTATION |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 50.00 |
| Cumulative Total Capacity (MW) | 50.00 |
| MW Effective From | 2030-10-31 |
| Project Status | Scoping |
| HOST TO | SHET |
| Plant Type | Energy Storage System |
| Project ID | a0l8e0000011zr5AAA |
| Project Number | PRO-003597 |
| Gate | 1 |
| Original text | Scoping |
| source_record_id | csv:row:2 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:2
Sources EV-20b891c892d345b9cbafa3d2Evidence SHA-256 2feb369e26e2a57bf5656824c32190410d8889b1e9d9a06a1bbb6c2c3e49f21b
행 SHA-256 65d0c18b4389db4d7b59b4b12d77fcd42f91d3741a3f5781d1f241d22cf5f79d
Usage terms NESO Open Data Licence