FACILITY INTELLIGENCE
Facility at a glance
kt cloud 청라 AI 데이터센터 · Plan
Permit, construction and use-approval milestones reflect the scope of each documented record.
Current status
Current facility status and operating features
Plan · 2026년 4분기 착공 목표 발표 · 실제 본공사 착수 미확인
Distinguish total facility capacity from capacity currently available to lease.
- Operation and development
- kt cloud (운영 예정)
- Facility type
- AI 데이터센터 개발계획
- Building and facility size
- Unverified
- Verify data
- 2026-11-20
Loading project participants…
FACILITY PROFILE
About this data center
인천 서해 · AI 데이터센터 개발계획Some original descriptions below are in Korean. Request an English review of this facility →
청라IDC PFV가 원창동381-73 일원에서 추진하고 kt cloud가 DBO로 참여하는 AI 데이터센터 계획이다. 수전50MW는 운영사가 발표한 설계 용량이다.
- 012026년 4분기 착공 목표 발표 · 실제 본공사 착수 미확인
- 02계획수전50MW(kt cloud 2026-10-07 발표). 전기사용계약·통전은 미확인.
LOCATION & ACCESS
Location and surrounding area
상세주소 확인 · 사업 신용평가 자료는 대표필지 외 1필지로 기재한다. 공시의 원창동381-74와 최종 허가부지 전체 목록의 대응은 추가 확인이 필요하다.
Location obtained by geocoding the published address.
FACILITIES & SERVICES
Facilities and operating features
Based on public information for this facility.- Operating and Development Entities
- kt cloud (운영 예정)
- Facility type
- AI 데이터센터 개발계획
- Building and facility size
- Unverified
- Public Power
- 계획수전50MW(kt cloud 2026-10-07 발표). 전기사용계약·통전은 미확인.
- Project Phases
- Plan
- Opening and announced dates
- 2026년 4분기 착공 목표 발표 · 실제 본공사 착수 미확인
How to interpret the specifications
사업 신용평가 자료는 대표필지 외 1필지로 기재한다. 공시의 원창동381-74와 최종 허가부지 전체 목록의 대응은 추가 확인이 필요하다. 계획수전50MW(kt cloud 2026-10-07 발표). 전기사용계약·통전은 미확인.
Utility power, UPS capacity and IT load are separate measures. Total facility capacity is also distinct from capacity currently available for occupancy.
Colocation and lease terms
Loading space availability and lease terms…
Want to know the colocation conditions at this center?
The center name is prefilled in your inquiry. Add your required capacity and timing if known.
You can submit an initial inquiry without signing up.Participants and investment
Loading participants, investments and delivery history…
Development and completion history
Permitting and development history
Plan · Check the scope of each building permit, construction start and use approval record.
Search the permit register →- Operation and opening
- 2026년 4분기 착공 목표 발표 · 실제 본공사 착수 미확인
Power, cooling and building
Loading power, cooling and building specifications…
Sources and review history
SOURCES & UPDATES
Sources and review dates
The source date is the date stated in the document; the review date is when it was checked. These differ from facility completion and operation start dates.Public source documents 5records · latest check 2026-11-20
- 01
- 02
- 03
- 04
- 05
Power, area, cooling and certification information is limited to what has been published. Available capacity, pricing and contract terms require confirmation with the operator.