Operations began in 2020
KT Cloud Yongsan Data Center
33 Wonhyo-ro 41-gil, Yongsan-gu, Seoul
Distinguish between power supply, UPS, and IT load
Commercial and Hyperscale
Confirm move-in conditions at this center.
Discuss facility, power and network requirements → · Compare published Korean rental productsCENTER OVERVIEW
About the Center
As a hyperscale commercial data center in central Seoul, it is a key hub for KT Cloud, featuring a high-capacity backbone and 154 kV power infrastructure.
AI-DC KOREA ANALYSIS
Interpretation and Verification Points
The 400 MW figure on the official page refers to the design capacity for power supply expansion, not the current IT load. It must be displayed separately from the currently disclosed total UPS capacity of 40.8 MW, and the available rental capacity requires confirmation from the operator.
Power supply capacity refers to the range of power designed and contracted to be received from KEPCO; UPS capacity refers to the size of the uninterruptible power supply system; and IT load refers to the power actually allocated to IT equipment. Do not make estimates unless these are distinguished in the published data.
Cross-Reference Data and Licensing Detail Ledger
We publish basic information about the centers and their official legal basis. For links to candidate sites by data source, as well as details on permits, groundbreaking, and occupancy permits—including any changes—please refer to Research Pro.