Carscreugh
Connection register · built
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 15.2 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-ad649ffd59ffb6c043392cb9 |
| MW Increase / Decrease | 0 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-ad649ffd59ffb6c043392cb9 |
| Cumulative Total Capacity (MW) | 15.2 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-ad649ffd59ffb6c043392cb9 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Carscreugh |
| Customer Name | SP DISTRIBUTION PLC |
| Connection Site | Glenluce 132/33kV |
| Stage | Not obtained |
| MW Connected | 15.20 |
| MW Increase / Decrease | 0.00 |
| Cumulative Total Capacity (MW) | 15.20 |
| MW Effective From | Not obtained |
| Project Status | Built |
| HOST TO | SPT |
| Plant Type | Wind Onshore |
| Project ID | a0l4L0000005ihrQAA |
| Project Number | PRO-000772 |
| Gate | Not obtained |
| Original text | Built |
| source_record_id | csv:row:125 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:125
Sources EV-ad649ffd59ffb6c043392cb9Evidence SHA-256 2feb369e26e2a57bf5656824c32190410d8889b1e9d9a06a1bbb6c2c3e49f21b
행 SHA-256 2cab2065e8af6f0897163e65a354f5886267a79b97335c9cd73cbad0be560361
Usage terms NESO Open Data Licence