Australia · Generator · plant location

Boro Hybrid Solar Farm and BESS

공식 원천의 전력 객체 · Plan

Project stage · source basis
Planned / preconstruction · planned
Reported operator
Check each original source
Address
Check each original source
Data Reference Date
2026-07-31
Collection review date
2026-10-05
Location meaning
Location meaning unverified · Accuracy not disclosed
Coordinates and geometry
Coordinates need review

These are source records. Operator labels do not confirm legal ownership or operations. Map locations do not verify supplying substations, power contracts or current available capacity.

Power assets and projects · AUS · aemo_generation

Boro Hybrid Solar Farm and BESS

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Unit Capacity (MW DC)4.2 MWdcOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-ae7ef777c77be5226574b27a
Unit Capacity (MW AC)4.2 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-ae7ef777c77be5226574b27a
Aggregated Nameplate Capacity (MW DC)361.2 MWdcOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-ae7ef777c77be5226574b27a
Aggregated Nameplate Capacity (MW AC)361.2 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-ae7ef777c77be5226574b27a
Agg Nameplate Storage Capacity (MWh)1032 MWhOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-ae7ef777c77be5226574b27a
Detailed source fields
Original source fieldPublished value or condition
Survey ID3277
Site NameBoro Hybrid Solar Farm and BESS
Site OwnerSAMSUNG C&T RENEWABLE ENERGY AUSTRALIA PTY LTD
RegionNSW1
Max Site Capacity (AC)300
Gen Info Unit ID327703
Unit NameBoro BESS
Technology TypeBattery Storage
Technology DetailLithium-ion
Dispatch TypeScheduled
Unit Count86
Unit Capacity (MW DC)4.2
Unit Capacity (MW AC)4.2
Aggregated Nameplate Capacity (MW DC)361.2
Aggregated Nameplate Capacity (MW AC)361.2
Agg Nameplate Storage Capacity (MWh)1032
Commitment StatusPublicly Announced
Full Commercial Use Date2029-10-31T00:00:00
Expected Closure Year2059
Survey Latest Update Date2026-05-19T13:44:02
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:167

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:167

Sources EV-ae7ef777c77be5226574b27a
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 97650a4e07c05a0b0958a924030ae4f845a61b7c9b7f7d88e75ef1c5728360bd

Usage terms AEMO general copyright permission subject to exceptions