Australia · Generator · plant location

Ben Bullen Wind Farm

공식 원천의 전력 객체 · Plan

Project stage · source basis
Planned / preconstruction · planned
Reported operator
Check each original source
Address
Check each original source
Data Reference Date
2026-07-31
Collection review date
2026-10-05
Location meaning
Location meaning unverified · Accuracy not disclosed
Coordinates and geometry
Coordinates need review

These are source records. Operator labels do not confirm legal ownership or operations. Map locations do not verify supplying substations, power contracts or current available capacity.

Power assets and projects · AUS · aemo_generation

Ben Bullen Wind Farm

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Unit Capacity (MW DC)7.2 MWdcOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-7426353872bbb62523bf0594
Unit Capacity (MW AC)7.2 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-7426353872bbb62523bf0594
Aggregated Nameplate Capacity (MW DC)460.8 MWdcOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-7426353872bbb62523bf0594
Aggregated Nameplate Capacity (MW AC)460.8 MWacOriginal source column definition · Generation-register unit · Publicly Announced
As-of date 2026-07-31
Sources EV-7426353872bbb62523bf0594
Detailed source fields
Original source fieldPublished value or condition
Survey ID3180
Site NameBen Bullen Wind Farm
Site OwnerAlinta Energy
RegionNSW1
Max Site Capacity (AC)430
Gen Info Unit ID318001
Unit NameBBWF_GU1
Technology TypeWind
Technology DetailOnshore
Dispatch TypeSemi-scheduled
Unit Count64
Unit Capacity (MW DC)7.2
Unit Capacity (MW AC)7.2
Aggregated Nameplate Capacity (MW DC)460.8
Aggregated Nameplate Capacity (MW AC)460.8
Commitment StatusPublicly Announced
Full Commercial Use Date2032-01-31T00:00:00
Expected Closure Year2067
Survey Last Requested Date2026-03-10T00:00:00
Survey Latest Update Date2026-04-02T10:55:49
record_semanticsparticipant_reported_generation_information_not_DC_supply
Original textPublicly Announced
source_record_idGenerator Information:93

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
aemo_generation ↗

Data Source 2026-07-31 · Retrieved 2026-10-05

Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.

Source location Generator Information:93

Sources EV-7426353872bbb62523bf0594
Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 71e296c4a0e76e58e80e132b6c51023b6ce9f05d58fbda9963e54d50c4f8ecfc

Usage terms AEMO general copyright permission subject to exceptions

Related power and facility evidence

Loading related evidence…

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel