Blacktop BESS
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Unit Capacity (MW DC) | 4.2 MWdc | Original source column definition · Generation-register unit · Anticipated As-of date 2026-07-31 Sources EV-574ee57bba5439ee5a39ac3a |
| Unit Capacity (MW AC) | 4.2 MWac | Original source column definition · Generation-register unit · Anticipated As-of date 2026-07-31 Sources EV-574ee57bba5439ee5a39ac3a |
| Aggregated Nameplate Capacity (MW DC) | 168 MWdc | Original source column definition · Generation-register unit · Anticipated As-of date 2026-07-31 Sources EV-574ee57bba5439ee5a39ac3a |
| Aggregated Nameplate Capacity (MW AC) | 168 MWac | Original source column definition · Generation-register unit · Anticipated As-of date 2026-07-31 Sources EV-574ee57bba5439ee5a39ac3a |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Survey ID | 2305 |
| Site Name | Blacktop BESS |
| KCI Id | S00028 |
| Site Owner | Aquila Capital |
| Region | SA1 |
| Max Site Capacity (AC) | 100 |
| Gen Info Unit ID | 230501 |
| Unit Name | BBS_GU1 |
| Technology Type | Battery Storage |
| Technology Detail | Lithium-ion |
| Dispatch Type | Scheduled |
| Unit Count | 40 |
| Unit Capacity (MW DC) | 4.2 |
| Unit Capacity (MW AC) | 4.2 |
| Aggregated Nameplate Capacity (MW DC) | 168 |
| Aggregated Nameplate Capacity (MW AC) | 168 |
| Commitment Status | Anticipated |
| Full Commercial Use Date | 2029-06-30T00:00:00 |
| Expected Closure Year | 2059 |
| Survey Last Requested Date | 2026-03-10T00:00:00 |
| Survey Latest Update Date | 2026-06-17T15:55:22 |
| record_semantics | participant_reported_generation_information_not_DC_supply |
| Original text | Anticipated |
| source_record_id | Generator Information:117 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 2items
Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:117
Sources EV-574ee57bba5439ee5a39ac3aEvidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 5d6b5dcbacdb43961d91bcb2e16297c29c7fca20e1f1cfd1d19d6cbb923995f1
Usage terms AEMO general copyright permission subject to exceptions
Data Source 2026-07-24 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Expected Closure Year:51
Sources EV-f468c85f4e4ebb47df707493Evidence SHA-256 b945b7cf176e649d71ddaf90c4eb96eb1d2f197a592a98f1b4067ea1df56cbe8
행 SHA-256 c516daa3b62e56def7137c7afa55d53dddc939f96829e03428c8ce8743b542b3
Usage terms AEMO general copyright permission subject to exceptions