NFD 안산 성곡동 데이터센터 계획
경기도 안산시 단원구 성곡동
Public source documents 1 · Last reviewed 2026-11-21
Facility specification · separate from current availability
Facility rack count · separate from remaining inventory
Separate from gross floor and building area
FACILITY INTELLIGENCE
Facility at a glance
NFD 안산 성곡동 데이터센터 계획 · Plan
Permit, construction and use-approval milestones reflect the scope of each documented record.
Current status
Current facility status and operating features
Plan · 2027년: 1분기 착공 계획 · 개소일 미공 items
Distinguish total facility capacity from capacity currently available to lease.
- Operation and development
- NFD Korea(개발)
- Facility type
- 상업용 데이터센터 개발계획
- Building and facility size
- 계획 대지 8,248㎡ · 연면적 24,953㎡
- Verify data
- 2026-11-21
Loading project participants…
FACILITY PROFILE
About this data center
Ansan, Gyeonggi Province · 상업용 데이터센터 개발계획Some original descriptions below are in Korean. Request an English review of this facility →
NFD Korea가 자체개발 사업으로 공개한 안산 성곡동 데이터센터입니다.
- 01자체개발 프로젝트
- 02IT 부하와 수전용량 구분
LOCATION & ACCESS
Location and surrounding area
행정구역 확인 · 공개된 사업권역입니다. 개별 필지·건물과 정확한 시설 위치는 아직 확인되지 않았습니다.
The map shows the area center. The facility address and site boundary are not confirmed.
FACILITIES & SERVICES
Facilities and operating features
Based on public information for this facility.- Operating and Development Entities
- NFD Korea(개발)
- Facility type
- 상업용 데이터센터 개발계획
- Building and facility size
- 계획 대지 8,248㎡ · 연면적 24,953㎡
- Public Power
- 계획: IT 부하 28MW · 설계 PUE 1.33 · 수전·계약전력 미공 items
- Project Phases
- Plan
- Opening and announced dates
- 2027년: 1분기 착공 계획 · 개소일 미공 items
How to interpret the specifications
사업자 일정에는 2026년 7월 인허가와 2027년 1분기 착공이 제시되어 있습니다. 날짜만으로 실제 허가·착공 완료를 확정하지 않으며, 같은 사이트의 별도 안산 컨설팅 프로젝트와 구분합니다.
Utility power, UPS capacity and IT load are separate measures. Total facility capacity is also distinct from capacity currently available for occupancy.
Colocation and lease terms
Loading space availability and lease terms…
Want to know the colocation conditions at this center?
The center name is prefilled in your inquiry. Add your required capacity and timing if known.
You can submit an initial inquiry without signing up.Participants and investment
Loading participants, investments and delivery history…
Development and completion history
Permitting and development history
Plan · Check the scope of each building permit, construction start and use approval record.
Search the permit register →- Operation and opening
- 2027년: 1분기 착공 계획 · 개소일 미공 items
Power, cooling and building
Loading power, cooling and building specifications…
Sources and review history
SOURCES & UPDATES
Sources and review dates
The source date is the date stated in the document; the review date is when it was checked. These differ from facility completion and operation start dates.Public source documents 1records · latest check 2026-11-21
- 01
Power, area, cooling and certification information is limited to what has been published. Available capacity, pricing and contract terms require confirmation with the operator.
Suggest a correction or provide information →Loading linked supporting evidence…
Loading additional records…
Review source reference dates and review dates together. Facility specifications and operation information have a different scope from current supply terms.