Data Center Database/LG Uplus/Anyang, Gyeonggi Province
● Operations

LG U+ Pyeongchon Mega Center

29, Simin-daero 327beon-gil, Dongan-gu, Anyang-si, Gyeonggi-do

Center OverviewPhysical Sites · PowerSame operator
Operational StatusOperations

Operations began in 2015

Public PowerPower intake capacity: 165 MW

Distinguish between power supply, UPS, and IT load

Facility SizeTotal floor area: 85,548 square meters; data center area: 8,400 pyeong

Commercial and Telecommunications

Confirm move-in conditions at this center.

Discuss facility, power and network requirements → · Compare published Korean rental products

CENTER OVERVIEW

About the Center

As a high-density commercial IDC in the Pyeongchon area of Anyang, it is a key hub with the largest publicly disclosed power capacity within LG Uplus’s official network of centers.

01Disclosed power reception capacity: 165 MW
02Uptime Tier III Design Certification Label
03Dual hubs in the same region as Pyeongchon 2 Center

AI-DC KOREA ANALYSIS

Interpretation and Verification Points

165 MW is the maximum power capacity that can be supplied by KEPCO and is not equivalent to the IT load. Official information states an average of 8 kW per rack, Tier III uptime design certification, and a configuration of two data centers.

Principles for Interpreting Numbers

Power supply capacity refers to the range of power designed and contracted to be received from KEPCO; UPS capacity refers to the size of the uninterruptible power supply system; and IT load refers to the power actually allocated to IT equipment. Do not make estimates unless these are distinguished in the published data.

RESEARCH PRO

Cross-Reference Data and Licensing Detail Ledger

We publish basic information about the centers and their official legal basis. For links to candidate sites by data source, as well as details on permits, groundbreaking, and occupancy permits—including any changes—please refer to Research Pro.