POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 33items · current page 1–33 · Source records, not unique facilities.
Power assets and projects · AUS · aemo_generation Boco Rock Wind Farm Generator · Operations
Metric or condition Source value Basis, scope and stage Unit Capacity (MW AC) 1.6 MWac Original source column definition · Generation-register unit · In Service As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 Aggregated Nameplate Capacity (MW AC) 14.4 MWac Original source column definition · Generation-register unit · In Service As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8
Detailed source fields Original source field Published value or condition Survey ID 1022 Site Name Boco Rock Wind Farm Site Owner Tilt Renewables Australia Pty Ltd Region NSW1 Max Site Capacity (AC) 113 Gen Info Unit ID 102202 Unit Name Boco Rock Wind Farm:59-67 Technology Type Wind Technology Detail Onshore DUID BOCORWF1 Dispatch Type Semi-scheduled Unit Count 9 Unit Capacity (MW AC) 1.6 Aggregated Nameplate Capacity (MW AC) 14.4 Commitment Status In Service Expected Closure Year 2040 Survey Last Requested Date 2026-03-10T00:00:00 Survey Latest Update Date 2026-03-31T09:23:13 record_semantics participant_reported_generation_information_not_DC_supply Original text In Service source_record_id Generator Information:134
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 2items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
aemo_closure ↗ Data Source 2026-07-24 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Expected Closure Year:58
Sources EV-ea00061b687dc8b6497494f8 Evidence SHA-256 b945b7cf176e649d71ddaf90c4eb96eb1d2f197a592a98f1b4067ea1df56cbe8 행 SHA-256 1af6cf9f99869fd40a5498697032614941b52713cd56dfc6dfe5ea9a77e88ab5 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Region NSW1 AEMO Survey ID 1022 Gen Info Unit ID 102202 Site Name Boco Rock Wind Farm DUID BOCORWF1 Commitment Status In Service Expected Closure Year 2040 Survey Latest Update Date 2026-03-31T09:23:13 Publication Date 2024-07-24T00:00:00 record_semantics participant_reported_generation_information_not_DC_supply Original text In Service source_record_id Expected Closure Year:58
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items aemo_closure ↗ Data Source 2026-07-24 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Expected Closure Year:58
Sources EV-ea00061b687dc8b6497494f8 Evidence SHA-256 b945b7cf176e649d71ddaf90c4eb96eb1d2f197a592a98f1b4067ea1df56cbe8 행 SHA-256 1af6cf9f99869fd40a5498697032614941b52713cd56dfc6dfe5ea9a77e88ab5 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Survey ID 1022 Site Name Boco Rock Wind Farm Site Owner Tilt Renewables Australia Pty Ltd Region NSW1 Max Site Capacity (AC) 113 Gen Info Unit ID 102202 Unit Name Boco Rock Wind Farm:59-67 Technology Type Wind Technology Detail Onshore DUID BOCORWF1 Dispatch Type Semi-scheduled Unit Count 9 Unit Capacity (MW AC) 1.6 Aggregated Nameplate Capacity (MW AC) 14.4 Commitment Status In Service Expected Closure Year 2040 Survey Last Requested Date 2026-03-10T00:00:00 Survey Latest Update Date 2026-03-31T09:23:13 record_semantics participant_reported_generation_information_not_DC_supply Original text In Service source_record_id Generator Information:134
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2033-34
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2028-29
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2030
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2026
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2031-32
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2030-31
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2027-28
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2032
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2034
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2032-33
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2027
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2026-27
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2031
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2026-27
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2031-32
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2028-29
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2035-36
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2034-35
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2029-30
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2028
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2035
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2032-33
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2033
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2035-36
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2033-34
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2027-28
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 13.608 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Peak 2029-30
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2030-31
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Summer Typical 2034-35
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset Metric or condition Source value Basis, scope and stage Scheduled Capacity 14.58 MW Not obtained · Generation-register unit · Forecast As-of date 2026-07-31 Sources EV-7d044efd7af373769b941ab8 측정·전망기간 Winter 2029
Seasonal generation-capacity forecast; not metered data-center demand.
Sources, reference dates and retrieval dates 1items aemo_generation ↗ Data Source 2026-07-31 · Retrieved 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
Source location Generator Information:134
Sources EV-7d044efd7af373769b941ab8 Evidence SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d 행 SHA-256 b8e29ed436c63ccd803eaf98bdcb4c197d733f5421641a200e277cd9c8daeb82 Usage terms AEMO general copyright permission subject to exceptions
Observations for this power asset