Development and PermittingOfficial Source Text

Confirm the schedule for the Gimpo ICN11 construction amendment contract and the contract expiration in May 2028

In a corrective disclosure by DL E&C, details regarding the revised contract amount, project site, planned IT load, and contract period for the Gimpo ICN11 project—commissioned by Digital Seoul 2—were confirmed.

Release Date2026-08-27
Project SiteGimpo, Gyeonggi Province
Parties involvedDigital Seoul 2, Digital Realty, DL E&C
Current StageConstruction and Contract Amendments

VERIFIED FACTS

Key points identified in the original text

01Project Site: 6877-9, Gurae-dong, Gimpo-si, Gyeonggi-do
02Planned IT Load: 64 MW; 4 basement levels / 8 above-ground levels
03Construction contract amount: 489,059,755,158 won (excluding VAT)
04Contract period: May 25, 2025 – May 31, 2028

AI-DC KOREA ANALYSIS

Interpretation and the following points to verify

Since this is an amendment to the construction contract for the same ICN11 project in Gurae-dong, Gimpo, it has not been registered as a duplicate entry for a new center. The amount of 489,059,755,158 won is the construction contract amount excluding VAT; it is not the total project cost or the amount raised through project financing (PF). The 64 MW figure represents the planned IT load and should be distinguished from power supply capacity, UPS capacity, and current operational capacity. The contract expiration date of May 31, 2028, should not be assumed to be the date of commencement of operations or the date of completion approval.

PRIMARY EVIDENCE

Source Materials

The external source text is provided for fact-checking purposes; the summary and stage-by-stage analysis have been organized on this page.
Korea Exchange (KRX), KIND, and Koscom DisclosuresConfirm the schedule for the Gimpo ICN11 construction amendment contract and the contract expiration in May 20282026-08-27 · Open original text ↗