Facility at a glance
인천공항 항공 AI 혁신허브 · Plan
Permit, construction and use-approval milestones reflect the scope of each documented record.
Current status
Current facility status and operating features
Plan · 2026년 2월 우선협상대상자 선정·실시협약 후 4년 이내 준공 조건
Distinguish total facility capacity from capacity currently available to lease.
- Operation and development
- 씨티디벨롭먼트 컨소시엄(우선협상대상자)
- Facility type
- 항공 AI 데이터센터·R&D 복합개발
- Building and facility size
- 대지 23,302.4㎡(공모 기준)
- Verify data
- 2026-11-21
Loading project participants…
FACILITY PROFILE
About this data center
인천 영종 · 항공 AI 데이터센터·R&D 복합개발Some original descriptions below are in Korean. Request an English review of this facility →
인천국제공항공사가 운서동 3233-37에 추진하는 항공 AI 데이터센터·연구개발 복합사업입니다. 공사는 2026년 2월 10일 씨티디벨롭먼트 컨소시엄을 우선협상대상자로 발표했습니다.
- 01운서동 공모 대상 필지 확인
- 02계약전력 40MW 미만 조건
- 03우선협상대상자 선정
LOCATION & ACCESS
Location and surrounding area
상세주소 확인 · 공항공사 모집안내서의 대상 필지입니다. 문서상 옛 중구 주소를 현행 영종구로 표기했습니다.
Location obtained by geocoding the published address.
FACILITIES & SERVICES
Facilities and operating features
Based on public information for this facility.- Operating and Development Entities
- 씨티디벨롭먼트 컨소시엄(우선협상대상자)
- Facility type
- 항공 AI 데이터센터·R&D 복합개발
- Building and facility size
- 대지 23,302.4㎡(공모 기준)
- Public Power
- 공모조건: 계약전력 40MW 미만. 22.9kV 상시 2·예비 2회선 또는 154kV 상시 1·예비 1회선 선택안. 실제 공급계약 미확인.
- Project Phases
- Plan
- Opening and announced dates
- 2026년 2월 우선협상대상자 선정·실시협약 후 4년 이내 준공 조건
How to interpret the specifications
40MW 미만은 모집안내서의 계약전력 상한 조건입니다. 수전방식과 연계설비는 공항공사 협의 및 사업시행자의 인허가를 전제로 하며, 실시협약 체결·착공·통전의 완료를 뜻하지 않습니다.
Utility power, UPS capacity and IT load are separate measures. Total facility capacity is also distinct from capacity currently available for occupancy.
Colocation and lease terms
Loading space availability and lease terms…
Want to know the colocation conditions at this center?
The center name is prefilled in your inquiry. Add your required capacity and timing if known.
You can submit an initial inquiry without signing up.Participants and investment
Loading participants, investments and delivery history…
Development and completion history
Permitting and development history
Plan · Check the scope of each building permit, construction start and use approval record.
Search the permit register →- Operation and opening
- 2026년 2월 우선협상대상자 선정·실시협약 후 4년 이내 준공 조건
Power, cooling and building
Loading power, cooling and building specifications…
Sources and review history
SOURCES & UPDATES
Sources and review dates
The source date is the date stated in the document; the review date is when it was checked. These differ from facility completion and operation start dates.Public source documents 2records · latest check 2026-11-21
- 01
- 02
Power, area, cooling and certification information is limited to what has been published. Available capacity, pricing and contract terms require confirmation with the operator.
Suggest a correction or provide information →Loading linked supporting evidence…
Loading additional records…
Review source reference dates and review dates together. Facility specifications and operation information have a different scope from current supply terms.