캄스퀘어 용인지곡 데이터센터 계획
경기도 용인시 기흥구 지곡동 236-6 외 2필지
Public source documents 2 · Last reviewed 2026-11-21
Facility specification · separate from current availability
Facility rack count · separate from remaining inventory
Separate from gross floor and building area
FACILITY INTELLIGENCE
Facility at a glance
캄스퀘어 용인지곡 데이터센터 계획 · Plan
Permit, construction and use-approval milestones reflect the scope of each documented record.
Current status
Current facility status and operating features
Plan · 2026년 3월 전력공급설비 설계계약 확인
Distinguish total facility capacity from capacity currently available to lease.
- Operation and development
- 캄스퀘어용인데이터센터PFV(시행)
- Facility type
- 하이퍼스케일 데이터센터 개발사업
- Building and facility size
- 대지 약 32,082㎡ 계획(개발 보도 기준)
- Verify data
- 2026-11-21
Loading project participants…
FACILITY PROFILE
About this data center
Yongin, Gyeonggi Province · 하이퍼스케일 데이터센터 개발사업Some original descriptions below are in Korean. Request an English review of this facility →
캄스퀘어용인데이터센터PFV가 발주한 용인지곡 데이터센터 사업입니다. 한국전력기술은 2026년 3월 27일 전력공급·부대설비 설계계약 체결을 발표했습니다.
- 01345kV 지중 수전선로 설계
- 02수전 60MW·IT 40MW 계획 구분
- 03실제 착공·공급개시 추가 확인
LOCATION & ACCESS
Location and surrounding area
상세주소 확인 · 한전기술의 발주 PFV·지곡동 사업과 정확 필지 보도를 대조했습니다.
Location obtained by geocoding the published address.
FACILITIES & SERVICES
Facilities and operating features
Based on public information for this facility.- Operating and Development Entities
- 캄스퀘어용인데이터센터PFV(시행)
- Facility type
- 하이퍼스케일 데이터센터 개발사업
- Building and facility size
- 대지 약 32,082㎡ 계획(개발 보도 기준)
- Public Power
- 60MW급 개발계획·345kV 지중 수전선로 설계계약. 수전 60MW·IT 40MW는 계획 보도 기준이며 실제 공급개시는 미확인.
- Project Phases
- Plan
- Opening and announced dates
- 2026년 3월 전력공급설비 설계계약 확인
How to interpret the specifications
한전기술의 업무에는 345kV 지중 수전선로 설계와 기자재 구매·인허가 지원이 포함됩니다. 설계계약 단계와 전기사용계약·실제 착공을 구분합니다. 위탁운영 계약은 롯데이노베이트 관련 보도에서 확인되며 준공 이후 운영을 전제로 합니다.
Utility power, UPS capacity and IT load are separate measures. Total facility capacity is also distinct from capacity currently available for occupancy.
Colocation and lease terms
Loading space availability and lease terms…
Want to know the colocation conditions at this center?
The center name is prefilled in your inquiry. Add your required capacity and timing if known.
You can submit an initial inquiry without signing up.Participants and investment
Loading participants, investments and delivery history…
Development and completion history
Permitting and development history
Plan · Check the scope of each building permit, construction start and use approval record.
Search the permit register →- Operation and opening
- 2026년 3월 전력공급설비 설계계약 확인
Power, cooling and building
Loading power, cooling and building specifications…
Sources and review history
SOURCES & UPDATES
Sources and review dates
The source date is the date stated in the document; the review date is when it was checked. These differ from facility completion and operation start dates.Public source documents 2records · latest check 2026-11-21
- 01용인 데이터센터 전력설비 설계용역 계약체결 ↗
Korea Electric Power Technology
Source reference date 2026-04-01 · Observed 2026-11-21
- 02
Power, area, cooling and certification information is limited to what has been published. Available capacity, pricing and contract terms require confirmation with the operator.
Suggest a correction or provide information →Loading linked supporting evidence…
Loading additional records…
Review source reference dates and review dates together. Facility specifications and operation information have a different scope from current supply terms.