Separate from IT, UPS and standby power
부산에코델타 그린데이터센터 PFV 계획
부산광역시 강서구 에코델타시티 그린데이터센터 집적단지
Public source documents 2 · Last reviewed 2026-11-21
Facility specification · separate from current availability
Facility rack count · separate from remaining inventory
Separate from gross floor and building area
FACILITY INTELLIGENCE
Facility at a glance
부산에코델타 그린데이터센터 PFV 계획 · Investment Agreements and Plans
Permit, construction and use-approval milestones reflect the scope of each documented record.
Current status
Current facility status and operating features
Investment Agreements and Plans · 전력공급 개시 2028년 6월 1일 예정 · 준공 2028년 상반기 목표(사업자 발표)
Distinguish total facility capacity from capacity currently available to lease.
- Operation and development
- 부산에코델타그린데이터센터 PFV(시행)
- Facility type
- 계획 단계 상업용 데이터센터
- Building and facility size
- 개별: 부지·건축규모 미공 items
- Verify data
- 2026-11-21
Loading project participants…
FACILITY PROFILE
About this data center
Gangseo, Busan · 계획 단계 상업용 데이터센터Some original descriptions below are in Korean. Request an English review of this facility →
부산에코델타그린데이터센터 PFV가 추진하는 에코델타시티 사업입니다.
- 01투자협약·부지계약 확인
- 02개별 사업으로 구분
LOCATION & ACCESS
Location and surrounding area
사업구역 확인 · 공개된 사업권역입니다. 개별 필지·건물과 정확한 시설 위치는 아직 확인되지 않았습니다.
The map shows the area center. The facility address and site boundary are not confirmed.
FACILITIES & SERVICES
Facilities and operating features
Based on public information for this facility.- Operating and Development Entities
- 부산에코델타그린데이터센터 PFV(시행)
- Facility type
- 계획 단계 상업용 데이터센터
- Building and facility size
- 개별: 부지·건축규모 미공 items
- Public Power
- 사업자 발표: 상용 300MW·예비 300MW 전기사용계약(2026년 8월 보도) · 계약서 원문·실제 통전 미확인
- Project Phases
- Investment Agreements and Plans
- Opening and announced dates
- 전력공급 개시 2028년 6월 1일 예정 · 준공 2028년 상반기 목표(사업자 발표)
How to interpret the specifications
2026년 8월 시행자는 전기사용계약 체결과 345kV 수전계획을 발표했습니다. 상용과 예비 용량을 600MW 연속사용능력으로 합산하지 않습니다. 계약원문과 실제 전력공급 개시는 별도 확인이 필요합니다.
Utility power, UPS capacity and IT load are separate measures. Total facility capacity is also distinct from capacity currently available for occupancy.
Colocation and lease terms
Loading space availability and lease terms…
Want to know the colocation conditions at this center?
The center name is prefilled in your inquiry. Add your required capacity and timing if known.
You can submit an initial inquiry without signing up.Participants and investment
Loading participants, investments and delivery history…
Development and completion history
Permitting and development history
Investment Agreements and Plans · Check the scope of each building permit, construction start and use approval record.
Search the permit register →- Operation and opening
- 전력공급 개시 2028년 6월 1일 예정 · 준공 2028년 상반기 목표(사업자 발표)
Power, cooling and building
Loading power, cooling and building specifications…
Sources and review history
SOURCES & UPDATES
Sources and review dates
The source date is the date stated in the document; the review date is when it was checked. These differ from facility completion and operation start dates.Public source documents 2records · latest check 2026-11-21
- 01
- 02에코델타시티 입주5개사 선정 및 협약 현황 ↗
Busan Metropolitan City
Source reference date 2024-03-04 · Observed 2026-11-21
Power, area, cooling and certification information is limited to what has been published. Available capacity, pricing and contract terms require confirmation with the operator.
Suggest a correction or provide information →Loading linked supporting evidence…
Loading additional records…
Review source reference dates and review dates together. Facility specifications and operation information have a different scope from current supply terms.