critical it design capacity · キャンパス · as published 基準日 2024-03-12 根拠 EV-a7e7b8419fb2eafcd4b05126
原出典の詳細項目
原出典項目
公開値・条件
esa_signed_period
2023-08
substation_voltage_kV
275
energization_reported_by
2024-03-12
exact_energization_date
未取得
contracted_supply_MW
未取得
inherited_batch
AIDC-GLOBAL-20261005-DATA-R1-FIX1
eligible_for_exact_contract_mw
false
検証状況
primary_statement
変更種類
enriched
契約当事者
名称
Yondr
役割
data_center_developer
機関ID
未取得
検証状況
name_in_primary_source_not_registry_verified
名称
Tenaga Nasional Berhad
役割
electricity_supplier
機関ID
未取得
検証状況
name_in_primary_source_not_registry_verified
Announcement expressly describes IT load, despite being in an ESA paragraph. Contract gross/grid MW is not disclosed. Displayed date March 12; release dateline March 13, 2024. 300 MW is critical IT campus design capacity, not ESA MW. Source announces campus substation energized without an exact event date.