critical it design capacity · 园区 · as published 基准日期 2024-03-12 依据 EV-a7e7b8419fb2eafcd4b05126
原始来源详细字段
原始来源字段
公开数值或条件
esa_signed_period
2023-08
substation_voltage_kV
275
energization_reported_by
2024-03-12
exact_energization_date
未获取
contracted_supply_MW
未获取
inherited_batch
AIDC-GLOBAL-20261005-DATA-R1-FIX1
eligible_for_exact_contract_mw
false
验证状态
primary_statement
变更类型
enriched
合同当事方
名称
Yondr
角色
data_center_developer
机构ID
未获取
验证状态
name_in_primary_source_not_registry_verified
名称
Tenaga Nasional Berhad
角色
electricity_supplier
机构ID
未获取
验证状态
name_in_primary_source_not_registry_verified
Announcement expressly describes IT load, despite being in an ESA paragraph. Contract gross/grid MW is not disclosed. Displayed date March 12; release dateline March 13, 2024. 300 MW is critical IT campus design capacity, not ESA MW. Source announces campus substation energized without an exact event date.