| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| MW Connected | 0 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-e1b53665bc614471b3e50420 |
| MW Increase / Decrease | 150 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-e1b53665bc614471b3e50420 |
| Cumulative Total Capacity (MW) | 150 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-e1b53665bc614471b3e50420 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Project Name | Arresgill Wind Farm |
| Customer Name | ARRESGILL ENERGY LIMITED |
| Connection Site | Arresgill 132kV Substation |
| Stage | 未获取 |
| MW Connected | 0.00 |
| MW Increase / Decrease | 150.00 |
| Cumulative Total Capacity (MW) | 150.00 |
| MW Effective From | 2031-10-31 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | SPT |
| Plant Type | Wind Onshore |
| Project ID | a0l4L0000005ikZQAQ |
| Project Number | PRO-002409 |
| Gate | 1 |
| 原文状态 | Scoping |
| source_record_id | csv:row:82 |
位置: 未获取坐标 · 不在地图标注
原文、基准日期与核实日期 1条
数据来源 2026-10-01 · 收集核实 2026-10-05
Supported by National Energy SO Open Data
原文位置 csv:row:82
依据 EV-e1b53665bc614471b3e50420资料SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480