Alverdiscott Farm
接続登録 · scoping
| 指標・条件 | 出典の値 | 基準・範囲・段階 |
|---|---|---|
| MW Connected | 0 MW | 原出典の列定義 · project stage · Scoping 基準日 2026-10-01 根拠 EV-e8a07c368945733640124b8e |
| MW Increase / Decrease | 1000 MW | 原出典の列定義 · project stage · Scoping 基準日 2026-10-01 根拠 EV-e8a07c368945733640124b8e |
| Cumulative Total Capacity (MW) | 1000 MW | 原出典の列定義 · project stage · Scoping 基準日 2026-10-01 根拠 EV-e8a07c368945733640124b8e |
原出典の詳細項目
| 原出典項目 | 公開値・条件 |
|---|---|
| Project Name | Alverdiscott Farm |
| Customer Name | Alverdiscott 10 Renewables Ltd |
| Connection Site | Alverdiscott 400kV Substation |
| Stage | 未取得 |
| MW Connected | 0.00 |
| MW Increase / Decrease | 1000.00 |
| Cumulative Total Capacity (MW) | 1000.00 |
| MW Effective From | 2037-04-24 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | NGET |
| Plant Type | Energy Storage System;PV Array (Photo Voltaic/solar) |
| Project ID | a0l4L000002yQZtQAM |
| Project Number | PRO-002554 |
| Gate | 未取得 |
| 原文の状態 | Scoping |
| source_record_id | csv:row:58 |
位置: 座標未取得・地図表示なし
原文・基準日・確認日 1件
資料の基準 2026-10-01 ・取得確認 2026-10-05
Supported by National Energy SO Open Data
原文内の位置 csv:row:58
根拠 EV-e8a07c368945733640124b8e資料SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480