| Unit Capacity (MW AC) | 72 MWac | 原出典の列定義 · 発電登録単位 · In Service 基準日 2026-07-31 根拠 EV-0a203be0d95eb320c19e12d8 |
| Aggregated Nameplate Capacity (MW AC) | 72 MWac | 原出典の列定義 · 発電登録単位 · In Service 基準日 2026-07-31 根拠 EV-0a203be0d95eb320c19e12d8 |
原出典の詳細項目
| 原出典項目 | 公開値・条件 |
|---|---|
| Survey ID | 1217 |
| Site Name | Upper Tumut |
| Site Owner | Snowy Hydro Ltd |
| Region | NSW1 |
| Max Site Capacity (AC) | 665 |
| Gen Info Unit ID | 121708 |
| Unit Name | Upper Tumut:8 |
| Technology Type | Hydro |
| Technology Detail | Dam |
| DUID | UPPTUMUT |
| Dispatch Type | Scheduled |
| Unit Count | 1 |
| Unit Capacity (MW AC) | 72 |
| Aggregated Nameplate Capacity (MW AC) | 72 |
| Commitment Status | In Service |
| Expected Closure Year | 2070 |
| Survey Last Requested Date | 2026-03-10T00:00:00 |
| Survey Latest Update Date | 2026-05-19T16:30:51 |
| record_semantics | participant_reported_generation_information_not_DC_supply |
| 原文の状態 | In Service |
| source_record_id | Generator Information:1570 |
位置: 座標未取得・地図表示なし
原文・基準日・確認日 2件
資料の基準 2026-07-31 ・取得確認 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
原文内の位置 Generator Information:1570
根拠 EV-0a203be0d95eb320c19e12d8資料SHA-256 36e64862b715d7edaa736a9bb9c2f73559d63f6b3d1f7afe693e66d7beee038d
행 SHA-256 b871a918ce63e6375aa38984e0c8ef7853234fcdd477cc04e892303b8c8c2535
利用条件 AEMO general copyright permission subject to exceptions
資料の基準 2026-07-24 ・取得確認 2026-10-05
Australian Energy Market Operator (AEMO), Generation Information, July 2026; normalized by DATA.
原文内の位置 Expected Closure Year:738
根拠 EV-ca369a0a46027d11a89785c7資料SHA-256 b945b7cf176e649d71ddaf90c4eb96eb1d2f197a592a98f1b4067ea1df56cbe8
행 SHA-256 d82d44a651f1298093c7e674fcf8e2938d3f4d87eaad497f7e78ed9fb06aa05d
利用条件 AEMO general copyright permission subject to exceptions