근거 EV-1a7214996e37d633bef2ee46 자료 SHA-256 f70420e5f2ae99cb7db8393fbebe03a59727b20187d959aec62ab51ab1dd090a · inherited_normalized_file전력 관측 · USA · primary:ae1b30ffcdc10e1e998b3fa4
contracted grid connection capacity · 미공개 · as published 기준일 2025-08-28 근거 EV-1a7214996e37d633bef2ee46
원출처 세부 필드
원출처 항목
공개값·조건
inherited_batch
AIDC-GLOBAL-20261005-DATA-R1-FIX1
eligible_for_exact_contract_mw
true
검증 상태
primary_statement
변경 유형
reused
계약 당사자
2025 filing documents executed grid connection agreements and connection deposits. A 2026-09-08 operator update says Sweetwater substation is energized, 300MW gross construction targets Q4 2027, and ERCOT Batch Zero classifications remain conditional. This is not 1,400MW operational IT load.