Amersham Main
接入登记 · scoping
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| MW Connected | 0 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-db5454735658d681073a1f94 |
| MW Increase / Decrease | 1000 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-db5454735658d681073a1f94 |
| Cumulative Total Capacity (MW) | 1000 MW | 原始来源列定义 · project stage · Scoping 基准日期 2026-10-01 依据 EV-db5454735658d681073a1f94 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Project Name | Amersham Main |
| Customer Name | Amersham 10 Renewables Limited |
| Connection Site | London North West Connection Node A 400kV Substation |
| Stage | 未获取 |
| MW Connected | 0.00 |
| MW Increase / Decrease | 1000.00 |
| Cumulative Total Capacity (MW) | 1000.00 |
| MW Effective From | 2037-10-31 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | NGET |
| Plant Type | Energy Storage System;PV Array (Photo Voltaic/solar) |
| Project ID | a0l8e000000TPQWAA4 |
| Project Number | PRO-003404 |
| Gate | 未获取 |
| 原文状态 | Scoping |
| source_record_id | csv:row:64 |
位置: 未获取坐标 · 不在地图标注
原文、基准日期与核实日期 1条
数据来源 2026-10-01 · 收集核实 2026-10-05
Supported by National Energy SO Open Data
原文位置 csv:row:64
依据 EV-db5454735658d681073a1f94资料SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 bf497a935495eec3aa6efe1b4c2ac63153d4fb1fb0109492d29a5d1c54579b28