Bethlehem Energy Center, LLC - (VA) / BETHL
发电机 · 计划
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 20 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-65cb067d0f657c1f6f389f64 |
| Net Summer Capacity (MW) | 20 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-65cb067d0f657c1f6f389f64 |
| Net Winter Capacity (MW) | 20 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-65cb067d0f657c1f6f389f64 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 67449 |
| Entity Name | East Point Energy, LLC |
| Plant ID | 70231 |
| Plant Name | Bethlehem Energy Center, LLC - (VA) |
| Google Map | Map |
| Bing Map | Map |
| Plant State | VA |
| County | Prince William |
| Balancing Authority Code | PJM |
| Sector | IPP Non-CHP |
| Generator ID | BETHL |
| Nameplate Capacity (MW) | 20 |
| Net Summer Capacity (MW) | 20 |
| Net Winter Capacity (MW) | 20 |
| Technology | Batteries |
| Energy Source Code | MWH |
| Prime Mover Code | BA |
| Planned Operation Month | 10 |
| Planned Operation Year | 2026 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 38.781889 |
| Longitude | -77.5426 |
| 原文状态 | (U) Under construction, less than or equal to 50 percent complete |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Planned:307 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Proposed:2684
依据 EV-774c765b6c47164afbb92ac0资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 3fe3183a08664cdd7628131b8b8a2d67174aa1474490123e62b6ad8138467a7e
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Planned:307
依据 EV-65cb067d0f657c1f6f389f64资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 01d1519fb78a369f6bf42f8027aeb7d9e94fd2d9cd29d3f93a7b581980aa5774