Pointe Coupee Power Station / PC3B
发电机 · 计划
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 311 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-bfa8eef48f021cd5b81fad39 |
| Net Summer Capacity (MW) | 302.8 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-bfa8eef48f021cd5b81fad39 |
| Net Winter Capacity (MW) | 311 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-bfa8eef48f021cd5b81fad39 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 11241 |
| Entity Name | Entergy Louisiana LLC |
| Plant ID | 69944 |
| Plant Name | Pointe Coupee Power Station |
| Google Map | Map |
| Bing Map | Map |
| Plant State | LA |
| County | Pointe Coupee |
| Balancing Authority Code | MISO |
| Sector | Electric Utility |
| Generator ID | PC3B |
| Unit Code | PC03 |
| Nameplate Capacity (MW) | 311 |
| Net Summer Capacity (MW) | 302.8 |
| Net Winter Capacity (MW) | 311 |
| Technology | Natural Gas Fired Combined Cycle |
| Energy Source Code | NG |
| Prime Mover Code | CA |
| Planned Operation Month | 12 |
| Planned Operation Year | 2031 |
| Status | (P) Planned for installation, but regulatory approvals not initiated |
| Latitude | 30.739 |
| Longitude | -91.377 |
| 原文状态 | (P) Planned for installation, but regulatory approvals not initiated |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Planned:2304 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Proposed:2472
依据 EV-3020798d467395bd4bdcd740资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 fe20daa96ee4a5cc370fd7e1d04fe2454ff6c66270eb82e93e2048c876c75895
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Planned:2304
依据 EV-bfa8eef48f021cd5b81fad39资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 cf3261a111e3dde5d30d612113acba61ec6a1abbfd7abda79d73d3d002db106b