Deckerville Solar Park / DKVSP
发电机 · 计划
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 200 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-9a6dafe7812e379cd265e896 |
| Net Summer Capacity (MW) | 200 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-9a6dafe7812e379cd265e896 |
| Net Winter Capacity (MW) | 200 MW | 原始来源列定义 · 发电机 · (U) Under construction, less than or equal to 50 percent complete 基准日期 2026-08 依据 EV-9a6dafe7812e379cd265e896 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 5109 |
| Entity Name | DTE Electric Company |
| Plant ID | 69776 |
| Plant Name | Deckerville Solar Park |
| Google Map | Map |
| Bing Map | Map |
| Plant State | MI |
| County | Sanilac |
| Balancing Authority Code | MISO |
| Sector | Electric Utility |
| Generator ID | DKVSP |
| Nameplate Capacity (MW) | 200 |
| Net Summer Capacity (MW) | 200 |
| Net Winter Capacity (MW) | 200 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 11 |
| Planned Operation Year | 2028 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 44.5521 |
| Longitude | -82.7649 |
| 原文状态 | (U) Under construction, less than or equal to 50 percent complete |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Planned:1730 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Proposed:2161
依据 EV-b5ef93fb50ae890a096d75ab资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 22cb48f29ef7710adb1dfdc7cfa35c6934889bede1c653ff49439046ab258421
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Planned:1730
依据 EV-9a6dafe7812e379cd265e896资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 4447cbed794852c9a8f4ca14cb2719326e1985ea772f6c7d3a05f7c76bb8ecf0