Rock Island Generation Project / RIG1
发电机 · 计划
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 20.3 MW | 原始来源列定义 · 发电机 · (L) Regulatory approvals pending. Not under construction 基准日期 2026-08 依据 EV-b008362fc61e10d6905cab9a |
| Net Summer Capacity (MW) | 19.9 MW | 原始来源列定义 · 发电机 · (L) Regulatory approvals pending. Not under construction 基准日期 2026-08 依据 EV-b008362fc61e10d6905cab9a |
| Net Winter Capacity (MW) | 19.9 MW | 原始来源列定义 · 发电机 · (L) Regulatory approvals pending. Not under construction 基准日期 2026-08 依据 EV-b008362fc61e10d6905cab9a |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 67625 |
| Entity Name | Kerrville Public Utility Board Public Facility Corp |
| Plant ID | 69760 |
| Plant Name | Rock Island Generation Project |
| Google Map | Map |
| Bing Map | Map |
| Plant State | TX |
| County | Colorado |
| Balancing Authority Code | ERCO |
| Sector | Electric Utility |
| Generator ID | RIG1 |
| Nameplate Capacity (MW) | 20.3 |
| Net Summer Capacity (MW) | 19.9 |
| Net Winter Capacity (MW) | 19.9 |
| Technology | Natural Gas Internal Combustion Engine |
| Energy Source Code | NG |
| Prime Mover Code | IC |
| Planned Operation Month | 9 |
| Planned Operation Year | 2027 |
| Status | (L) Regulatory approvals pending. Not under construction |
| Latitude | 29.55068 |
| Longitude | -96.53675 |
| 原文状态 | (L) Regulatory approvals pending. Not under construction |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Planned:1032 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Proposed:2136
依据 EV-386a0a478feb2a91c9ce8f62资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 5e262925ab3cb6bf4bb284afd691171bc2d669bebd1698853d5ea3c865955bf3
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Planned:1032
依据 EV-b008362fc61e10d6905cab9a资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 8bfeff40a005d133a3eaee868ac59181b9d8cd367f6e330aa9b3754af31cdc8e