Sunrose Renewable Energy / SRSEB
发电机 · 计划
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 300 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-6bc7ef5674a4ed35cec1282f |
| Net Summer Capacity (MW) | 300 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-6bc7ef5674a4ed35cec1282f |
| Net Winter Capacity (MW) | 300 MW | 原始来源列定义 · 发电机 · (P) Planned for installation, but regulatory approvals not initiated 基准日期 2026-08 依据 EV-6bc7ef5674a4ed35cec1282f |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 64545 |
| Entity Name | Vesper Energy Development LLC |
| Plant ID | 68033 |
| Plant Name | Sunrose Renewable Energy |
| Google Map | Map |
| Bing Map | Map |
| Plant State | TX |
| County | Austin |
| Balancing Authority Code | ERCO |
| Sector | IPP Non-CHP |
| Generator ID | SRSEB |
| Nameplate Capacity (MW) | 300 |
| Net Summer Capacity (MW) | 300 |
| Net Winter Capacity (MW) | 300 |
| Technology | Batteries |
| Energy Source Code | MWH |
| Prime Mover Code | BA |
| Planned Operation Month | 12 |
| Planned Operation Year | 2027 |
| Status | (P) Planned for installation, but regulatory approvals not initiated |
| Latitude | 29.674226 |
| Longitude | -96.12137 |
| 原文状态 | (P) Planned for installation, but regulatory approvals not initiated |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Planned:1294 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Proposed:1034
依据 EV-e103ef96aa1d330c512d2386资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 aeee8ece5adf3293ced8fda63b315125a085b05a635709e6d76a7e80ad284442
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Planned:1294
依据 EV-6bc7ef5674a4ed35cec1282f资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 6446f1ddb6fa100375d5696d7e5ce071a5eeb0f6525365f2c4212df72f48a3e2