Tieton Dam Hydro Electric Project / UNIT2
发电机 · 运营
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 6.9 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-05611ed8e8577952a1107a6f |
| Net Summer Capacity (MW) | 6.9 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-05611ed8e8577952a1107a6f |
| Net Winter Capacity (MW) | 6.9 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-05611ed8e8577952a1107a6f |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 2507 |
| Entity Name | City of Burbank Water and Power - (CA) |
| Plant ID | 57496 |
| Plant Name | Tieton Dam Hydro Electric Project |
| Google Map | Map |
| Bing Map | Map |
| Plant State | WA |
| County | Yakima |
| Balancing Authority Code | PACW |
| Sector | Electric Utility |
| Generator ID | UNIT2 |
| Nameplate Capacity (MW) | 6.9 |
| Net Summer Capacity (MW) | 6.9 |
| Net Winter Capacity (MW) | 6.9 |
| Technology | Conventional Hydroelectric |
| Energy Source Code | WAT |
| Prime Mover Code | HY |
| Operating Month | 9 |
| Operating Year | 2006 |
| Status | (OP) Operating |
| Latitude | 46.658 |
| Longitude | -121.1287 |
| 原文状态 | (OP) Operating |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Operating:14935 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Operable:14935
依据 EV-a2a2623bb762d514eae7dab8资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2281ea6d5717149d2c17ac00d346673681279b67ddad103ce2220e42529b2507
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Operating:14935
依据 EV-05611ed8e8577952a1107a6f资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 d29b4773311f09c0b06b590d725088ed140d3430caa28da9a44f74ac244100ea