Monroe (MI) / 2
发电机 · 运营
| 指标或条件 | 原文数值 | 口径、范围及阶段 |
|---|---|---|
| Nameplate Capacity (MW) | 822.6 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-870a10a51542c4dcc47b3c36 |
| Net Summer Capacity (MW) | 773 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-870a10a51542c4dcc47b3c36 |
| Net Winter Capacity (MW) | 783 MW | 原始来源列定义 · 发电机 · (OP) Operating 基准日期 2026-08 依据 EV-870a10a51542c4dcc47b3c36 |
原始来源详细字段
| 原始来源字段 | 公开数值或条件 |
|---|---|
| Entity ID | 5109 |
| Entity Name | DTE Electric Company |
| Plant ID | 1733 |
| Plant Name | Monroe (MI) |
| Google Map | Map |
| Bing Map | Map |
| Plant State | MI |
| County | Monroe |
| Balancing Authority Code | MISO |
| Sector | Electric Utility |
| Generator ID | 2 |
| Nameplate Capacity (MW) | 822.6 |
| Net Summer Capacity (MW) | 773 |
| Net Winter Capacity (MW) | 783 |
| Technology | Conventional Steam Coal |
| Energy Source Code | SUB |
| Prime Mover Code | ST |
| Operating Month | 3 |
| Operating Year | 1973 |
| Planned Retirement Month | 12 |
| Planned Retirement Year | 2032 |
| Status | (OP) Operating |
| Latitude | 41.8906 |
| Longitude | -83.3464 |
| 原文状态 | (OP) Operating |
| 坐标精度 | source_precision_not_independently_surveyed |
| source_record_id | Operating:2606 |
Coordinates locate the plant, including when this record describes one generator.
位置: 电厂位置 · 非单台发电机位置
原文、基准日期与核实日期 2条
数据来源 2025 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 3_1_Generator_Y2025.xlsx#Operable:2597
依据 EV-cf4485c02c20e5e16e1ffc64资料SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 8b12f198b93e5453f710421e3de1ed10bf5fc35da5adc074a4dc6354aa1c3d50
数据来源 2026-08 · 收集核实 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
原文位置 Operating:2606
依据 EV-870a10a51542c4dcc47b3c36资料SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 78630aa8f2eb7c9140dbc11050c3726bab74d1a8ac197c865d79177247c553c9